There are three options on this panel.
-
Option 1, if selected, tells Robot Schedule to use the control and output options of the group control job for each member job in the group.
-
Option 2, if selected, tells Robot Schedule to end the group if a member job ends abnormally.
-
Option 3, if selected, tells Robot Schedule to use the start date from the group control job as the job date for all group member jobs.